It took us 470 days to build a Germany to India association with our Force MTU partnership

Client: FORCE MTU

Force MTU Power Systems is a joint venture between Force Motors and Rolls-Royce Power Systems AG. The former is a homegrown Indian automotive brand, while the latter is a German company that designs and manufactures industrial engines and parts. Force MTU combines the expertise of both to produce top-of-the-line engines for multiple applications. Notably for the Series 1600 engines for power generation and rail underfloor applications.

Force MTU's Requirement

Force MTU wanted to relocate their manufacturing operations from Germany to India. They aimed for the Chakan MIDC area near Pune as it was and still is an in-demand hub for various industries. Force MTU needed the assistance of an experienced and reliable developer-partner to undertake and complete such a project on time and with high- quality standards. In short, they wanted a modern and advanced specification plug-and-play facility.

IndoSpace's Solution

The IndoSpace Advantage

Force MTU conducted thorough research about the industrial real estate developers in and around the Chakan region. They sought information about those who had a proven track record of project delivery and technical capabilities. Post the assessment, IndoSpace was on board as Force MTU’s preferred developer-partner. We acquired complete knowledge about Force MTU’s requirements and suggested IndoSpace Industrial Park Chakan I Phase III as the new destination for their relocation to India.

Design, Technical, & Execution Expertise

Force MTU wanted their new manufacturing facility in Chakan to have a distinct process layout from its German plant. Following were the goals we jointly agreed upon for the intricate project:

Product quality must adhere to the client’s international team of experts. IndoSpace must provide 24-hour service utility maintenance and stable operations.

Availability of utilities and resources needed for the manufacturing unit must be secured, such as high-tension power connection, industrial water, sewer and storm line connection, internal bituminous road, vehicle parking, fire hydrant and sprinkler system, and security gate with CCTV.

IndoSpace would allot a total chargeable area of 0.18 mn sq. ft to the project along with a construction timeline of 470 days.IndoSpace must achieve project delivery within the agreed timelines.

Customisation & Sustainability

IndoSpace implemented several green initiatives for Force MTU to ensure efficient, sustainable, and environment-friendly operations were undertaken. It included the following features:

End-Result

IndoSpace completed a high-quality advanced-specification facility suiting client’s global standards within 470 days. Force MTU could commence its operations within the stated time frame.*The images displayed in the case studies and blogs indicate illustrative purposes and for your reference only. It may not be an absolute representation of the product and/or manufacturing process of our clients.

Enquire Now

Please enable JavaScript in your browser to complete this form.